扫码查看
强涌潮区的水域环境复杂多变,这极大增加了管袋围堰施工安全管理的难度.为确定强涌潮区管袋围堰施工从清基到维护阶段的安全管控重点,首先利用系统理论过程分析法(STPA)对施工安全风险因素进行定性分析,从人员、物资、管理、技术、环境5 个维度构建了强涌潮区管袋围堰施工安全风险指标体系;然后建立系统动力学(SD)演化模型,并运用网络层次分析法(ANP)确定各指标权重;最后结合工程实例进行模拟仿真.结果表明:随着工程推进以及对安全投入的逐步增加,管袋围堰施工安全风险水平呈现出先大幅上升,后逐步下降,最终趋于平缓的趋势;人员、物资是清基和吹填期影响施工安全的主要因素,而在排水和维护期,环境、管理是主要影响因素;人员、管理和环境这三因素对安全投入变化更为敏感.建议在施工过程中重视不同阶段之间的管控重点差异,及时转换管理策略并采取针对性措施以有效降低施工安全风险.
Simulation on safety risk of pipe bag cofferdam contruction in strong tidal bore area
The water environment in strong tidal areas is complex and changeable,which greatly increases the difficulty of safety management of pipe bag cofferdam construction.In order to determine the key points of management and control of bag cofferdams construction from foundation clearance to maintenance in strong tidal areas,system theory process analysis(STPA)was first used to conduct a qualitative analysis of construction safety risk factors from the five major aspects of personnel,materials,management,technology,and environment.Then a system dynamics(SD)evolution model was established,and the Analytical Network Hierar-chy Process(ANP)was used to determine the weight of each indicator.Finally simulations were conducted based on engineering examples.The results showed that with the advancement of the project and the gradual increase in safety investment,the safety risk level of pipe bag cofferdam construction showed a trend of first rising sharply,then gradually declining,and finally leveling off.Personnel and materials were the main influencing factors during the foundation clearing and filling period,while environment and management were the main influencing factors during the drainage and maintenance period.In addition,personnel,management and the environment were more sensitive to safety investment variation.Therefore,during the construction process,it is necessary to pay attention to the differences in management and control priorities between different periods,promptly switch management strategies and take targeted measures to effectively reduce construction safety risks.

construction safety riskpipe bag cofferdamstrong tidal boresystem theory process analysis(STPA)system dynamics(SD)

江新、赵力、张腾飞

展开 >

三峡大学 水利与环境学院,湖北 宜昌 443002

施工安全风险 管袋围堰 强涌潮区 系统理论过程分析(STPA) 系统动力学(SD)

国家自然科学基金

52179136

2024

人民长江
水利部长江水利委员会

人民长江

CSTPCD北大核心
影响因子:0.451
ISSN:1001-4179
年,卷(期):2024.55(5)
  • 24