人民长江2024,Vol.55Issue(6) :176-181,187.DOI:10.16232/j.cnki.1001-4179.2024.06.024

盾构隧洞预应力双层衬砌张拉施工及控制技术研究

Study on tension construction and control technology of prestressed double-layer lining of shield tunnels

谢强 陈昱弛 王彦东 陈宣 刘畅
人民长江2024,Vol.55Issue(6) :176-181,187.DOI:10.16232/j.cnki.1001-4179.2024.06.024

盾构隧洞预应力双层衬砌张拉施工及控制技术研究

Study on tension construction and control technology of prestressed double-layer lining of shield tunnels

谢强 1陈昱弛 1王彦东 1陈宣 1刘畅2
扫码查看

作者信息

  • 1. 中国水利水电第七工程局有限公司,四川 成都 610000;中国水利水电第七工程局成都水电建设工程有限公司,四川 成都 611100
  • 2. 西南交通大学 土木工程学院,四川 成都 610081
  • 折叠

摘要

预应力张拉是盾构隧洞预应力双层衬砌施工过程中的关键环节,良好的预应力张拉控制对于结构的整体使用寿命十分重要.基于珠江三角洲水资源配置工程某盾构隧洞,对预应力双层衬砌张拉施工技术进行了总结,采用有限元数值模拟进行应力控制验证,并鉴于现有实测数据缺陷提出了一种张拉钢绞线伸长量计算方法.结果表明:智能张拉施工技术具有高精度、高稳定性的特点;张拉结束后预应力混凝土衬砌结构全环受压,锚具槽为全环最不利位置,最大环向压应力为 14.0 MPa,未超过混凝土允许应力,结构整体受力安全;环锚钢绞线实际计算伸长量与规范允许值误差不超过6%,满足工程需求.研究成果可丰富输水隧洞预应力张拉施工及控制技术体系.

Abstract

Prestressed tension is a key link in the construction process of prestressed double-layer lining of water conveyance shield tunnels,precise prestressed tension control is very important for the overall service life of the structure.Based on a shield tunnel in the Pearl River Delta water resources allocation project,the tension construction technology of prestressed double-layer lining was summarized.The finite element numerical simulation was used to verify the stress control.In view of the defects of the existing measured data,a method for calculating the elongation of tensioned steel strand was proposed.The results showed that the intelligent tensioning construction technology had the characteristics of high precision and high stability.After the tension,the whole ring of the prestressed concrete lining structure was compressed,and the anchorage groove was the most unfavorable position of the whole ring.The maximum circumferential compressive stress was 14.0 MPa,which did not exceed the allowable stress of concrete,and the whole structure was safe.The error between the actual calculated elongation of the ring anchor steel strand and the allowable value of the specification did not exceed 6%,which met the engineering requirements.The research results enrich the prestressed tension and control technology system.

关键词

输水隧洞/预应力衬砌/预应力张拉控制/数值模拟/理论计算/珠江三角洲

Key words

water conveyance tunnel/prestressed tension lining/prestressed tension controlling/numerical simulation/theo-retical calculation/Pearl River Delta

引用本文复制引用

基金项目

国家自然科学基金(51991394)

出版年

2024
人民长江
水利部长江水利委员会

人民长江

CSTPCD北大核心
影响因子:0.451
ISSN:1001-4179
段落导航相关论文