首页|卡拉水电站倾倒岩体预应力锚索施工技术

卡拉水电站倾倒岩体预应力锚索施工技术

扫码查看
针对卡拉水电站枢纽区左岸边坡倾倒卸荷严重的实际情况,阐述了采用预应力锚索以改善边坡岩体的稳定性及应力状态的过程,并对锚索施工技术从锚索造孔设备的选型、施工参数的控制、注浆和锚索的锁定等工序进行了评价,取得了较好的效果.
Construction Technology of Prestressed Anchor Cable in the Rock Mass of Kala Hydropower Project
In view of the serious dumping and unloading of the left bank slope of the Kala Hydropower Project,this paper expounds the application of prestressed anchor cables to improve the stability and stress state of the slope rock mass,the technology of anchor cable construction is evaluated from the selection of anchor cable hole-making equipment,the control of construction parameters,grouting and anchor cable locking,and good re-sults have been achieved.

Landslide massPrestressAnchor cableKala Hydropower Project

王成、刘英

展开 >

中国水利水电第七工程局有限公司,四川 成都 610213

倾倒岩体 预应力 锚索 卡拉水电站

2024

四川水力发电
四川省水力发电工程学会

四川水力发电

影响因子:0.211
ISSN:1001-2184
年,卷(期):2024.43(5)