悬臂掘进机法在挤压性围岩隧道中的适应性研究——以木寨岭公路隧道为例

Adaptability of Cantilever Roadheader Construction Method in Squeezing Rock Tunnels:A Case Study of Muzhailing Highway Tunnel

扫码查看
为探明悬臂掘进机法应用于挤压性围岩隧道的可行性与具体效果,以木寨岭公路隧道为依托,首先开展基于工程地质条件的悬臂掘进机法适用性分析;其次,结合工程实施条件,对悬臂掘进机进行选型,并设计 2 台阶悬臂掘进开挖方案;最后,依托工程试验段,重点从施工效能和实施效果2 方面,开展2 台阶悬臂掘进机法和3 台阶钻爆法开挖的对比研究.研究结论如下:1)综合对岩石强度、开挖断面和工效 3 个因素进行分析,悬臂掘进机选型应重点考虑切割面积和切割功率.2)木寨岭公路隧道围岩按能否较好适应于悬臂掘进机法开挖,可划分为 2 类 6 种.3)对比 3 台阶钻爆法开挖的施工效能,2 台阶悬臂掘进机法的施工进度提高20%,平均超挖减少 150 mm,用工量减少 5~10 人,喷混凝土超耗量减少 57%.4)对比 3 台阶钻爆法开挖的围岩位移、压力、拱架应力和锚索轴力,2 台阶悬臂掘进机法中围岩压力减小 0.01~0.11 MPa;围岩位移和拱架应力最终量值无明显变化,但分布更均匀、更快趋于恒值;锚索平均轴力增大 39 kN.
In this study,a case study is conducted on the Muzhailing highway tunnel to explore the feasibility and applicable effects of the cantilever roadheader construction method in squeezing rock tunnels based on engineering geological conditions.The types of cantilever roadheader are selected according to the project implementation conditions,and a two-bench excavation scheme for the cantilever roadheader is designed and developed.Furthermore,a comparative analysis is conducted on two-bench excavation by a cantilever roadheader and three-bench excavation for drilling and blasting in a test section in terms of construction efficiency and effect.The main findings are summarized as follows:(1)The selection of the cantilever roadheader should focus on the cutting area and power according to rock strength,excavation cross-section,and work efficiency;(2)The surrounding rocks of the Muzhailing highway tunnel can be divided into two categories and six types based on the applicability of cantilever roadheader;(3)Compared with the construction efficiency of the three-bench drilling and blasting method,the two-bench cantilever roadheader construction method can increase construction advance by 20%and reduce average over-excavation,labor consumption,and shotcrete overconsumption by 150 mm,5-10 persons,and 57%,respectively;(4)Compared with the three-bench drilling and blasting method,the surrounding rock pressure is reduced by 0.01-0.11 MPa using the two-bench cantilever roadheader construction method with a stable and evenly-distributed final surrounding rock displacement and arch frame stress.Moreover,the average stress of the anchor cable is increased by 39 kN.

squeezing rock tunnelcantilever roadheader constructiondrilling and blasting excavationfield test

唐绍武、郭新新、于家武、龙文华

展开 >

中铁隧道局集团有限公司,广东 广州 511458

成都理工大学环境与土木工程学院,四川 成都 610059

中铁隧道集团二处有限公司,河北 三河 065201

挤压性围岩隧道 悬臂掘进机法 钻爆法 现场试验

国家自然科学基金

52308391

2024

隧道建设(中英文)
中铁隧道集团有限公司洛阳科学技术研究所

隧道建设(中英文)

CSTPCD北大核心
影响因子:0.785
ISSN:2096-4498
年,卷(期):2024.44(1)
  • 12