为探究新建双线隧道下穿施工对既有隧道结构造成的影响,以昆明地铁盾构下穿既有隧道施工项目为依托工程,以穿越角度、净距与地层损失率为影响因素,针对双线盾构开挖对既有隧道变形规律进行研究;通过模型试验分析地表沉降量、净距以及地层损失率之间的关系,并利用数值模拟进行对比验证.结果表明:(1)穿越角度与地层损失率为定值时,净距与地表沉降量呈负相关,与竖向最大位移正相关;穿越角度与净距为定值时,地层损失率与地表沉降变化呈正相关,与竖向最大位移正相关.(2)随净距增加,地表沉降槽曲线由"W"形逐渐向"U"形过渡,地表沉降最大值向双线隧道中心轴线移动,沉降最大值为13.96 mm;而随着地层损失率增加,地表沉降槽过渡成"W"形,沉降最大值出现在隧道左、右线中轴线上,为21.94 mm.(3)模型试验与数值分析结果相互验证,可为最大沉降值超过控制值提供预警信息.
Study on Deformation Effect of Double-Line Shield Tunneling Under the Existing Tunnel Construction
In order to explore the influence of underpass construction of new double-line tunnel on the existing tunnel structure,based on the Kunming Metro shield underpass tunnel construction project,the crossing angle,clear distance and formation loss rate are taken as influencing factors,and the deformation rule of the existing tunnel caused by double-line excavation is studied.The relationship between surface settlement,clear distance and formation loss rate is analyzed by model test and verified by numerical simulation.The results show that:(1)when the crossing angle and the formation loss rate are constant,the clear distance is negatively correlated with the surface settlement and positively correlated with the vertical maximum displacement.(2)With the increase of the net distance,the surface settlement trough curve gradually transitions from'W'to'U' shape,and the maximum surface settlement moves to the central axis of the double-line tunnel,and the maximum settlement value is 13.96 mm;however,with the increase of formation loss rate,the surface settlement trough transitions into a'W'shape,and the maximum settlement appears on the central axis of the left and right lines of the tunnel,with the maximum value of 21.94 mm.(3)The results of model test and numerical simulation analysis are mutually verified,which can provide early warning information for the maximum settlement value exceeding the control value.

double-line shield tunnelunderpass constructionmodel testnumerical simulationconstruction deformation

高崇

展开 >

中铁十九局集团有限公司 北京 100176

双线盾构隧道 下穿施工 模型试验 数值模拟 施工变形

中铁十九局集团有限公司科技研究开发项目