时速600km高速磁浮铁路工程筹划关键技术研究

扫码查看
高速磁浮铁路为复杂的系统性工程,与一般的轮轨高铁有差异,不可照搬一般铁路的施工组织设计规范.收集大量磁浮铁路相关资料开展研究,得出结论:梁上板式轨道梁较整体式轨道梁在工程筹划方面更具优势;高速磁浮隧道采用矿山法施工时与普通隧道无本质差异,但开挖、支护台架等需要采用断面有效面积>120 m2 的设备;高速磁浮隧道采用盾构法施工时需要15.3 m外径大盾构设备;高速磁浮整体式轨道梁定子施工方案,定子在梁场中组装完成,梁场内设置总装车间,总装车间的主要功能是进行定子、功能件的组装及将组装后的功能件通过连接件固定在梁上;高速磁浮梁上板式轨道梁定子施工方案,定子在轨道板预制场内装配,在轨道板预制场内设置定子装配车间,装配定子铁芯、功能件等,并进行功能件防腐处理;高速磁浮三相线圈施工方案,线圈不在预制场内安装,线圈一般在现场采用定子线圈敷设车安装.高速磁浮低置线路轨道梁需要安装功能区和定子,低置线路轨道梁建议在整体式轨道梁预制场或轨道板预制场生产,并在总装车间安装功能区和定子.研究成果可为高速磁浮铁路工程筹划提供参考和拓宽思路.
Research on Key Technologies for Planning High-Speed Maglev Railway Projects with a Speed of 600 km/h
The high-speed maglev railway is different from general railway because it is complicated and systematic,and it cannot be copied from the construction organization design specifications of general railways.Collecting a large amount of maglev railway data and conducting research,conclusions are drawn:slab track beams have more advantages in engineering planning than integral track beams;when the high-speed maglev tunnel is constructed using mining method,there is no essential difference from general tunnels,but equipment with an effective cross-sectional area greater than 120 m2 is required for excavation and support platforms;when the high-speed maglev tunnel is constructed using shield tunneling method,a large shield tunneling equipment with an outer diameter of 15.3 meters is required;project plan for integral track beams stator:the stator is assembled in the beam factory,and a final assembly workshop is set up in the beam factory.The main function of the final assembly workshop is to assemble the stator and functional components,and fix the assembled functional components on the beam through connecting parts;construction plan for stator of high-speed maglev slab track beam:the stator is assembled in the track slab prefabrication yard,and a stator assembly workshop is set up in the track slab prefabrication yard to assemble the stator core,functional components,etc.,and anticorrosive paint is applied on the functional components;project plan for high-speed maglev three-phase coils:the coils are not installed in the prefabrication factory,and the coils are generally installed on construction site using stator coil laying vehicles.The high-speed maglev low rise track beam requires the installation of functional area and stator.It is recommended to produce the track beam in the integrated track beam prefabrication yard or track slab prefabrication yard,and install the functional area and stator in the final assembly workshop.The research results can provide reference and broaden ideas for the planning of high-speed maglev railway projects.

high-speed maglevengineering planningconstruction organizationstator

周成杰

展开 >

中国铁路设计集团有限公司 天津 300308

高速磁浮 工程筹划 施组 定子

中国铁路设计集团有限公司科技开发课题

2021A240206

2024

铁道建筑技术
中国铁道建筑总公司

铁道建筑技术

影响因子:0.539
ISSN:1009-4539
年,卷(期):2024.(3)
  • 14