兰新客专大梁隧道地震灾害复旧整治工程实践

扫码查看
地震灾害为地下铁路隧道结构安全带来巨大挑战,构筑物一旦遭受地震作用,其安全稳定性会受到极大影响.因此,及时有效修复地震灾害造成的损坏对于保障铁路运输安全稳定至关重要.本研究以兰新客专地震灾害复旧工程为例,概述青海门源地震基本情况,分析大梁隧道损坏现状,并提出完整的拱墙拆换、套衬加固和全环拆换整治方案.同时,对工程实际经验教训进行总结,并提出工法、指挥和机械运用的创新性方法.本研究可为后续灾后修复工作提供参考和指导.
Restoration Construction Practice for Daliang Tunnel of Lanzhou-Urumqi High-Speed Railway Under Earthquake Disaster
Earthquake disasters pose significant challenges to the safety of underground railway tunnel structures.Once structures are affected by earthquakes,their safety and stability are greatly compromised.Therefore,timely and effective repair of earthquake damage is crucial for ensuring the safety and stability of railway transportation.Taking the restoration project of the Lanzhou-Urumqi High-speed Railway after the earthquake as an example,this study outlines the basic information of the Menyuan earthquake,analyzes the damage to the Daoliang Tunnel,and proposes a comprehensive plan for arch wall replacement,lining reinforcement,and full reconstruction of damaged sections.Additionally,it summarizes the practical experiences and lessons learned from the project and provides innovative methods for construction methods,project management,and mechanical applications.This study serves as a reference and guidance for future post-disaster recovery efforts.

tunnelearthquakedisaster managementreinforcementexperience summary

王碧军

展开 >

中铁十一局集团第五工程有限公司 重庆 400037

隧道 地震 灾害处理 加固 经验总结