摘要

顶推力是管幕顶管施工反力墙设计以及顶管机选型重要参数.依托三亚河口通道项目管幕段工程,采用Persson接触模型对三圆咬合顶管顶推力进行研究,结合管土接触影响下的顶推力计算公式,分析顶推力与顶管咬合程度的关系,最后结合现场实测数据进行对比分析.结果表明:根据咬合程度不同,三圆咬合顶管接触压力合力为1.34~4.04 G;三亚河口通道项目三圆咬合顶管所需顶推力区间为7 416.6~8 781.6 kN;与现场实测数据进行对比,依据本研究得出的顶推力为现场实测顶推力最大值的 1.38 倍,具有一定的安全储备且能够节约成本,可供后续类似工程参考.

Abstract

The thrust force is a crucial parameter in the construction of pipe-jacking projects,the design of reaction walls,and the selection of pipe-jacking machinery.This study draws on the pipe-curtain section of the Sanya River Mouth Channel project and employs the Persson contact model to investigate the thrust force associated with the three-circular-ring interlocking pipe-jacking,considering the influence of soil-pipe contact on the thrust force calculation formula.Additionally,the study examines the correlation between the thrust force and the extent of pipe interlocking.The findings are further validated through a comparison with actual on-site measurement data.The study reveals that the combined contact pressure for the three-circular-ring interlocking pipe-jacking varies from 1.34 G to 4.04 G,depending on the level of interlocking.For the Sanya River Mouth Channel project,the estimated thrust force necessary for the three-circular-ring interlocking pipe-jacking is between 7 416.6 kN and 8 781.6 kN.When compared with on-site measurements,the formula-derived thrust force is determined to be 1.38 times the maximum measured value on-site,indicating a certain safety reserve and potential cost savings.These findings provide valuable insights for the design and execution of similar engineering projects in the future.

关键词

管幕法/咬合顶管/接触压力/顶推力

Key words

pipe curtain method/interlocking pipe jacking/contact pressure/thrust force