铁路技术创新2024,Issue(4) :168-174.DOI:10.19550/j.issn.1672-061x.2024.05.14.010

庐山站超大体量高架站房上跨营业线钢结构整体顶推关键技术

Key Technology for Overall Incremental Launching of Steel Structure of the Super-Iarge Elevated Station Building Overpassing the Operational Line at Lushan Railway Station

韩锋 王硕 马水生 康宽彬 李海龙 崔现良 赵聪
铁路技术创新2024,Issue(4) :168-174.DOI:10.19550/j.issn.1672-061x.2024.05.14.010

庐山站超大体量高架站房上跨营业线钢结构整体顶推关键技术

Key Technology for Overall Incremental Launching of Steel Structure of the Super-Iarge Elevated Station Building Overpassing the Operational Line at Lushan Railway Station

韩锋 1王硕 1马水生 2康宽彬 1李海龙 1崔现良 1赵聪1
扫码查看

作者信息

  • 1. 中铁建设集团有限公司,北京 100040
  • 2. 昌九城际铁路股份有限公司,江西南昌 330000
  • 折叠

摘要

针对天桥、连廊和高架站房组成的异形不等高钢结构体系整体跨铁路营业线施工难题,建立该结构体系的数值分析模型,对其顶推全过程进行模拟仿真分析,通过结构物关键部位的风洞试验,考虑极端温差、强风以及极端温差和强风耦合作用下,分析异形不等高结构体系整体跨营业线施工过程受力与变形情况.相应提出的施工方法能够满足异形不等高钢结构体系整体跨铁路营业线施工安全性要求.通过构建异形不等高钢结构体系整体跨越营业线施工风险监测预警系统,实现结构体系跨越营业线施工风险的定量评估和智能化预警.

Abstract

To address the challenges in constructing the special-shaped unequal-height steel structure system composed of an over-bridge,a corridor,and an elevated station building,overpassing the operational railway line,a numerical analysis model was developed.This model was used to conduct a simulation analysis on the entire incremental launching process.Through wind tunnel tests on critical parts of the structure,taking into account factors like extreme temperature differences,high winds,and the combined effects of these conditions,the load bearing and deformation characteristics of the special-shaped unequal-height structural system overpassing the operational railway line during the construction are analyzed.The proposed construction approach can satisfy the safety requirements for the special-shaped unequal-height steel structure system overpassing the operational railway line.A monitoring and early warning system for construction risks of the special-shaped unequal-height steel structure system overpassing the operational line was established to implement quantitative assessment and intelligent early warning of construction risks of the structural system overpassing the operational line.

关键词

庐山站/超大体量/异形不等高/整体顶推/跨营业线/模拟分析/风洞试验

Key words

Lushan Railway Station/super-large/special-shaped unequal-height/overall incremental launching/overpassing the operational line/simulation analysis/wind tunnel test