In order to solve the safe construction and high-quality performance of super-large caisson in long-period wave areas on the west coast of Africa,the wave monitoring data for 30 years in the construction area and the construction difficulties of the supporting project were investigated and analyzed.Based on the measured data of long-period waves in the sea area,the joint distribution and probability statistics of significant wave height and spectral peak period,as well as the conditions of continuous construction operation,were analyzed.The probability distribution law of significant wave height and spectral peak period and the most favorable working time of different projects were obtained,and the guiding opinions for construction operations in the sea area were given,which provides a basis for the research on the construction deployment of super-large caisson in long-period wave areas.
关键词
长周期波浪/作业条件/超大沉箱/工程施工
Key words
long-period waves/operating conditions/super-large caisson/engineering construction