首页|围堰灌注桩水下环保拆除技术研究及应用

围堰灌注桩水下环保拆除技术研究及应用

Research and application of underwater environmental protection demolition technology for cofferdam cast-in-place piles

扫码查看
海水取排水箱涵陆域段在基坑支护干环境施工完成后,需拆除陆域和海域箱涵对接口处的支护结构来完成海陆箱涵对接.为了解决传统液压破碎锤工艺受场地与设备站位影响只能依次拆除单根灌注桩的限制和对工期的影响,文章对裕龙岛炼化一体项目陆域段箱涵成排灌注桩+高压旋喷桩支护的水下拆除进行技术研究和应用,采用水下绳锯法切割灌注桩,利用海上箱涵安装时既有的大吨位起重船整体吊装,确定了绳锯切割设备、起重船整体吊装、吊装孔设计、吊索具等关键参数,实现灌注桩水下绿色、安全拆除,保证了项目顺利实施.
After the completion of the dry environment construction of foundation pit support,the support structure at the interface of the land and sea box culvert should be removed to complete the docking of the sea and land box culverts.In order to solve the limitation that the traditional hydraulic crushing hammer process can only dismantle cast-in-place piles in sequence due to the influence of site and equipment station location,and the impact on the construction period,this paper conducts technical research and application of the underwater dismantling of the pit supporting cofferdam with box culvert rows and high pressure jet grouting piles in the land section of Yulong Island refinery and chemical integrated project.The technology adopts underwater rope saw method to cut the cast-in-place pile,and uses the existing large-tonnage crane ship for integral lifting during the installation of the offshore box culverts to determine key parameters such as rope saw cutting equipment,integral lifting of crane,design of lifting hole and lifting attachments,realizing underwater green and safe dismantling of cast-in-place piles and ensuring the smooth implementation of the project.

cast-in-place pile cofferdamunderwater demolitionrope saw cuttingintegral lifting

王传鹏、吕护生、王明玉

展开 >

中交一航局第二工程有限公司,山东 青岛 266071

灌注桩围堰 水下拆除 绳锯切割 整体吊装

2024

中国港湾建设
中国交通建设股份有限公司

中国港湾建设

CSTPCD
影响因子:0.447
ISSN:1003-3688
年,卷(期):2024.44(10)